activity

When thinking about cost behavior, think about how the cost behaves in total. A variable cost is a cost that varies in total. The cost increases or decreases based on a related activity.

The formula for total variable cost is:

Total Variable Cost = Variable Rate X Activity

Assume a constant rate

For planning and decision making purposes, we assume that the variable rate is constant. This allows for a single variable in the calculations. Only the activity will change. Now, that is not always the case, but as long as we are within the relevant range for our decision, we can assume that the rate will stay the same.

But isn’t it fixed if the rate stays the same?

Remember that a variable cost varies in total. The rate might stay the same but once you multiply the rate by varying levels of activity, the total variable cost will change.

Imagine that you are selling candy bars as a fundraiser for a club to which you belong. Your cost is 50 cents per candy bar and the club sells the candy bars for $1 each. If the club sells 200 candy bars, what is the total variable cost? Is it 50 cents? No, that is the cost of a single candy bar. If you sell 200, you would need to multiply that by 50 cents for each of the candy bars sold.

200 candy bars X 50 cents per candy bar = $100

What if the club sold 500 candy bars? The total variable cost would be $250.

Here is a graph of the total variable cost of candy bars for the fundraiser:

Total Variable Cost

Notice that if no candy bars are sold, there is no cost. The more candy bars that are sold, the higher the cost. The cost line is a straight line. The slope of the line is equal to the variable rate. For each additional unit sold, the line increases at a rate of 50 cents. Think of the formula of a line: y=mx + b, where y is your y coordinate, x is your x coordinate, m is the slope and b is the y-intercept (the point where the line hits the y-axis).

The formula for total variable cost is: y=mx. The y-intercept for a variable cost is always zero because if there is no activity, there is no cost. Therefore, the line will always start at 0,0. The slope of the line, m, is your variable rate. The activity is x. See your math teacher was right when he or she told you you would use this stuff someday!

Frequently, you will see textbooks show the formula for the slope of a line as the formula for cost equations.

Related Videos

Cost Behavior: Fixed, Variable, Step and Mixed 

Fixed and Variable costs as per unit and total costs

Share This:

We have previously discussed cost objects and assigning costs to cost objects. One object that is used frequently by job costing.

Job costing is a cost allocation method used by companies that make custom products. Imagine a cabinet maker who makes custom cabinets for homes. Each cabinet is custom built based on measurements made inside the customer’s home. All jobs require different amounts of material, labor, and overhead. Therefore, each job has a unique total cost.

Direct costs are easy to assign to jobs. It is easy to calculate the total cost of direct materials based on the materials used in the job. Companies use job cost sheets to record the cost of materials used on the job.

Direct labor is easy to calculate as we know how much each of the employees earns per hour and how many hours the employees worked on the job. Employees track which jobs they are working on throughout the week so that direct labor costs can be added to the job cost sheets.

Overhead can cause problems for organizations that use job costing. Without allocating overhead to jobs, we do not have an accurate idea of the cost of the job. Since overhead is such a large part of the cost of operating a business, we cannot ignore it. So how do we allocate it?

We could wait until the end of the year, when we know actual numbers but that does not help us determine if our jobs are profitable when they are completed. If we waited until we had all the overhead spending calculated for the year, it would be January of 2017 before we know if jobs completed in 2016 were profitable or not. We can’t wait that long if we want to determine if we are making profit on our jobs.

We could use overhead costs for the current or previous month and apply those costs to the job, but what if our overhead costs vary greatly from month to month. For example, what if we get the annual renewal for our insurance policies in March. Those insurance policies cost $100,000. Is it ethical to allocate that $100,000 only to the jobs that are completed in March or April? No, those costs should be allocated to all jobs completed throughout the year, not just those unlucky customers who happened to place in order with our company in March or April.

If we don’t know the actual costs, how can we allocate overhead fairly to all of our jobs? We are going to use estimates.

Most businesses complete budgets prior to the beginning of each year. These budgets include estimated overhead and estimated activity. We can use those estimates to calculated a rate that we can apply to our jobs. We call this rate the predetermined overhead rate.

Predetermined overhead rate = Estimated Overhead / Estimated Activity

The company can choose any activity it believes will most accurately apply the overhead costs. Most companies use direct labor hours or machine hours to allocate overhead costs.

Example #1

K’s Premier Cabinets uses job costing to calculate the cost of jobs as they are completed. The company estimates that it will have $1,250,000 in overhead costs in 2015. The company believes that employees will work 200,000 hours and that 150,000 machine hours will be used during 2015. Calculate the predetermined overhead rate assuming that the company uses direct labor hours to allocate overhead to jobs.

Predetermined overhead rate is estimated overhead divided by estimated activity. The example states that estimated activity is 200,000 direct labor hours.

$1,250,000 / 200,000 direct labor hours = $6.25 per direct labor hour (don’t forget to label your numbers)

Applying the predetermined overhead rate to jobs

Alright, so we have a rate. Now what?

We must apply the rate to our jobs. The rate from our example above is $6.25 per direct labor hour. How do we apply this to our jobs? Based on the direct labor hours worked on the job. For each direct labor hour worked, we will add $6.25 of overhead to the job.

Applied overhead is overhead added to a job by taking the predetermined overhead rate multiplied by the actual activity. Applied overhead is added to direct materials and direct labor to calculate total job cost.

Total Job Cost = Direct Materials + Direct Labor + Applied Overhead

Every time a job is completed, overhead is applied to the job. The total cost of all the jobs completed over the course of the year is cost of goods sold.

Example #2

K’s Premier Cabinets completes job #322 on July 7. The job used 45 direct labor hours and 30 machine hours. The job consumed $1,800 worth of materials. The average direct labor rate is $18.00 per hour and the company uses the predetermined overhead rate calculated in Example #1. Calculate the total cost of job #322.

There are three components of job cost: direct materials, direct labor and applied overhead.

We are told that direct materials are $1,800.

We must calculate total direct labor cost. Direct labor is a variable cost. Our rate is $18.00 per direct labor hour. Our driver is 45 hours. If we calculate rate x activity, our total direct labor cost for job #322 is:

$18.00 per direct labor hour X 45 direct labor hours = $810

Lastly, we just apply overhead to the job. Overhead is applied by taking our predetermined overhead rate and multiplying it by activity. We are given activity for direct labor hours and for machine hours. Which one do we use? Remember when I said to label your answer? This is precisely why it is so important to label your rate! So what was our rate?

$6.25 per direct labor hour

Therefore, we are going to apply the rate based on direct labor hours.

$6.25 per direct labor hour X 45 direct labor hours = $281.25

We now have the components of job cost. Now to add them up and see what the total cost of the job is.

Direct materials = $1,800
Direct labor = $810
Applied overhead = $281.25
Total job cost = $2,891.25

Final Thoughts

One of the most important pieces of advice I can give you about allocating overhead using a predetermined overhead rate is keeping the terminology straight in your mind.

Estimated overhead is calculated at the beginning of the year before any work begins. Applied overhead is calculated throughout the year as jobs are completed and added to the cost of the jobs.

First calculate your predetermined overhead rate using estimates and LABEL YOUR ANSWER! Then apply overhead to jobs by using the predetermined overhead rate and actual activity.

Related Videos

Allocating overhead using a predetermined overhead rate

Job cost for service companies

Share This:


Related pages


balance sheet reconciliation examplemanagerial accounting job order costingreducing balance method depreciation formulasalvage value calculator carretire treasury stock journal entryformula for calculating sales taxjournal entries for depreciation of fixed assetmake or buy decision formulaindirect labor costgross profit fifowhat is closing entries in accountingvariable costing method income statementcalculating depreciation expense straight-line methodwip accounting treatmentspecimen of trial balancewhat types of accounts are referred to as temporary accountscogs calculationincome statement debits and creditscost drivers accountingsimple interest loan formulabad debt accounting entryprepare adjusting journal entriesprepaid insurance adjusting entry examplesbills payable journal entryhow to calculate variable cost per unitlifo ending inventoryfinancial accounting bookan accounting device used to analyze transactionsyear end inventory adjustment journal entrymonthly closing entriesvariable cost examples restaurantjournalizing transactions accountingcalculate factory overheadcalculating predetermined overhead rate managerial accountingtarget costing calculationwhen is bad debt expense recordedhow to find total fixed cost on a graphexample adjusting entriessalaries payable journal entryposting closing entriesoverhead cost variance issalary to biweekly pay calculatorweighted average formulastoatl jobsoverhead rate per direct labor costjournal entry of depreciationadvantages and disadvantages of weighted average cost methodwhat is the present value of an annuityprepaid journal entrytoo much social security tax withheldlifo vs fifo accountingtotal overhead variance formulahow to work out gp percentagegross method perpetual inventory system360 day loan calculatoroperating income margin formulaprepaid rent expense journal entryrumus marginal costpercent variation calculatorpresent value of ordinary annuity calculatorpresent value of an ordinary annuity of 1 tablefinancial accounting adjusting entriesdeprecation in accountingallowance for bad debt journal entryreversing journal entriesallowance for uncollectible accounts is classified asjournal entry worksheet accountingincremental margin calculationintroduction of sales and inventory systemcall option accounting journal entries